ASSEMBLY AND CHECKOUT
Saturn V stages are shipped to the Kennedy Space Center by ocean-going vessels or by specially designed aircraft. Apollo spacecraft modules are transported by air and delivered to the Manned Spacecraft Operations Building at Kennedy Space Center for servicing and checkout before mating with the Saturn V.
Saturn V stages go into the Vehicle Assembly Building low bay area where preparation and checkout begins. Receiving inspection and the low bay checkout operations are first performed before stages are erected within a high bay.
After being towed into the high bay area and positioned under the 250-ton overhead bridge crane. slings are attached to the first stage and hooked to the crane. The stage is positioned above the launch platform of the mobile launcher and lowered into place. Then it is secured to four holddown/support arms. These support the entire space vehicle during launch preparation and provide holddown during thrust buildup prior to launch.
Next, engine fairings are installed on the stage and fins are moved into position and installed in line with the four outboard engines.
Mobile launcher electrical ground support equipment is connected to the launch control center (LCC) via the high speed data link, and the test program is started with the actual launch control equipment.
Prior to and during this time, all low bay testing is completed and the upper stages are prepared for mating. The mating operation consists of stacking the stages. Umbilical connection begins immediately and continues during the mating operation on a noninterference basis. The vertical alignment of the vehicle is performed after each stage is mated.
When the launch vehicle is ready, the Apollo spacecraft is brought to the VAB and mated.
Checkout of all systems is performed concurrently in the high bay. The first tests provide power and cooling capability' to the vehicle, validate the connections, and establish instrumentation. When this is completed, systems testing begins. The systems tests are controlled and monitored from the LCC wherever practical and "break-in" tests are held to a minimum. Following the validation of each stage, a data review is held and the vehicle is prepared for combined systems tests.
The combined systems tests verify the flight- readiness of the overall vehicle. These tests include a malfunction sequence test, an overall test of the launch vehicle, an overall test of the spacecraft, and a simulated flight test. Prior to the simulated flight test, final ordnance installation is completed. After the test, vertical alignment is checked, a data review is held, and the vehicle is prepared for transfer to the pad. These preparations include disconnecting pneumatic, hydraulic, and electrical lines from the mobile launcher to the VAB.
After the lines are disconnected, the transporter is moved into position beneath the mobile launcher. Hydraulic jacks engage the fittings on the mobile launcher and raise it approximately 3 feet so that it clears its mount mechanisms. Then the transporter moves out of the VAB, over the crawlerway, to the launch pad.
TESTING AT LAUNCH SITE
At the launch pad, the transporter moves the mobile launcher into position, lowers and locks it onto another set of mount mechanisms. The transporter then moves to the mobile service structure parking area, picks up the service tower, and positions it beside the Saturn V to provide vehicle access for pad operations.
The digital data link, communications circuitry, pneumatic supply lines, propellant lines, environmental controls, and electrical power supply lines are connected.
Power again is applied to the vehicle and the control and monitor links are verified. Pad testing is held to a minimum. The high bay from which the vehicle was moved remains empty during pad operations.
A spacecraft systems verification test is performed, followed by a space vehicle cutoff and malfunction test. Radio frequency compatibility is established and preparations are made for a final flight readiness test, which involves sequence tests paralleling the actual countdown and inflight operations. Compatibility with the stations of the Eastern Test Range and the Integrated Mission Control Center in Houston, Tex., are verified at this time.
Following an evaluation of the flight readiness test, all systems are reconfigured for launch, and all plugs are reverified. A countdown-demonstration test is then performed as the final test prior to launch. The countdown-demonstrationtest consists of an actual launch countdown, complete with propellant loading, astronaut embarkation, etc., with the exception of actual ignition. This test exercises systems, the launch crew, and the astronauts, and prepares the "team" for the actual operation to follow. This "dress rehearsal" is used divulge any last minute problems and affords the mission a better chance of success.
Upon completion of the countdown demonstration test, the space vehicle is recycled to pre-count status, and preparations are made for the final countdown phase of launch operations. Normal recycle time between completion of the countdown demontration test and beginning of launch countdown is 48 to 72 hours.
Propellant loading of the Apollo spacecraft is performed prior to launch day. Aerozine 50 is the fuel, and nitrogen tetroxide the oxidizer. Also prior to launch day, hypergolics for the third stage reaction control system are loaded and ordnance connected. Loading of the cryogenic propellants for the launch vehicle begins on launch day at approximately T-7 hours. (The kerosene is loaded one day before launch.)
Liquid oxygen loading is begun first. The tanks are precooled before filling. Precool of one tank can be accomplished concurrently with the fill of another. Loading is started with the second stage to 40 percent, followed by the third stage to 100 percent. The second stage is then brought to a full 100 percent followed by loading the first stage to 100 per cent. This procedure allows time for the liquid oxygen leak checks to be performed prior to full loading of the second stage. Liquid oxygen is pumped at a flowrate of 1,000 gallons per minute for the third stage. For the second stage, the tank rate is 5,000 gallons per minute, and the first stage tank flow rate is 10,000 gallons per minute.
Liquid hydrogen loading is initiated next, beginning with the second stage to 100 per cent. Loading of the third stage liquid hydrogren is last. Liquid hydrogen is pumped to the second stage at a rate of 10,000 gallons per minute, and to the third stage at a rate of 3,000 gallons per minute. Topping of cryogenic tanks of the launch vehicle continues until launch. Total cryogenic loading time from start to finish is 4 hours and 30 minutes.
At approximately T-90 minutes, after propellants are loaded, the astronauts enter the spacecraft from the mobile launcher over the swing arm walkway.
LAUNCH
During the remainder of the countdown, the final systems checks are conducted.
Launch vehicle propellant tanks are then pressurized, and the first stage engines ignited. During the thrust buildup of the F-1 engines, the operation of each of these engines will be automatically checked. Upon confirmation of thrust OK condition, the launch commit signal is given to the holddown arms and liftoff occurs.